About this project

Asphalt overlay, drainage construction and solar street lighting along the principal township corridor.

Delivered under the Building Your Future Strategic Policy Framework in Kafur Local Government Area.

Verification record

Field-verified on 15 November 2025 · SAMPLE DATA — not a verified record.

Project record

Sector
Infrastructure
Implementing agency
Katsina State Ministry of Works
Budget allocation
₦20m
Kilometres delivered
17,904
Started
18 June 2023
Completed
13 April 2025